The State of the Data Center Supply Chain in 2023

June 13, 2023
Although delays and pricing issues persist for some equipment, the DCF Executive Roundtable consensus is that many elements of the supply chain have stabilized. A deep dive into the data center supply chain.

The delivery of new data center capacity has been complicated by disruptions in the global supply chain. Although delays and premium pricing persist for some equipment, data center executives say many elements of the supply chain have stabilized. 

That's the consensus of the data center thought leaders in our DCF Executive Roundtable for the Second Quarter of 2023, which continues today with a deep dive into the state of the supply chain.    

Here’s an introduction to our panel of industry experts:

Here's our conversation.

Data Center Frontier: How would you assess the state of the data center supply chain? What items continue to experience long lead times or availability problems?

Dave Young, DartPoints: The state of the data center supply chain remains challenging. Some elements show improvement and stabilization; however, lead times remain longer than traditionally expected. The supply chain challenges caused DartPoints to shift away from the JIT (just-in-time) mindset. Our talented team of managers has a forward-thinking mindset and has positioned our organization to manage our growth model to meet our clients’ needs. We identify the current market conditions and factor the supply chain delays in our strategic investments. Inventory management and strategic investment will continue to play an essential role in 2023, as we are not anticipating significant improvements.

We continue to see longer lead times and availability problems for large power distribution equipment and switchgear, including utility transformers. One of our partner electrical contractors commented that the industry is experiencing lead times of over one year across the board. Other power distribution and cooling infrastructure items remain challenging, where lead times are three to four months longer than traditional expectations. Critical power systems, such as generators and UPS, have stabilized with reasonable lead time expectations.

Our Infrastructure team has reported stabilization in the market with some improvement in lead times. To minimize the ongoing supply chain impact, DartPoints maintains an agile vendor network where we partner with our vendors to manage and mitigate risk. Our partnerships allow us to reduce and overcome the current supply chain challenges strategically and creatively.

Joe Goldsmith, NTT GDCA: Challenges in the global data center supply chain over the past few years have led to substantial price increases and extended lead times. In response, the industry has started ordering equipment early and locking in production slots, which has further constrained the market and created extended supplier backlogs.  

Some deliveries are now happening, whereas before there was a two-year delivery timeframe for most equipment. However, deliveries of everything electrical and mechanical remain a huge problem around the world. 

It’s still taking about two years to deliver uninterruptible power supplies or generators. There are also long lead times for items like transformers for substations, and even chillers are pushing 12 to 16 months. 

There have been some improvements in delivery of construction materials. We faced extended lead times for roofing, precast concrete and electrical components in 2022, but these now appear to have stabilized. The availability of construction labor has also improved in some geographies due to delays or pauses in other projects.

One hurdle that we have had to deal with is unpredictability in the delivery of equipment when there's an unanticipated need for certain components. Often, these needs only become clear closer to the equipment delivery date, which means our construction sites have had to become more proactive in equipment orders. We have therefore focused on working with our supply chain to mitigate these delivery delays.

Another global challenge is getting power to data centers from utility companies or other power providers. This is taking longer than expected because the ability of many of these utilities or providers to deliver power is tapped out. So, we’re forced to devise alternative ways of generating power for the data centers, which is causing an interesting shift in the data center industry here in the US, at least.

Rich Okoney, JLL: While data center supply chain issues have seen improvements over the past year, lead times and equipment availability continue to be a substantial headwind for the industry. Specifically, sourcing electrical equipment such as batteries, switchgear and generators efficiently, is still very problematic. The availability of those products is running 6-12 + months. This is largely being driven by raw materials shortages which are used to manufacture equipment. IT infrastructure is another area being affected. Instead of weeks to get these specific components, it often takes months.

Continued friction in the supply chain is leading to rising costs in the overall cost of data center expansions, upgrades and new builds. 

I see these persistent challenges leading to more adaptations in supply chain strategies. Not only is equipment being ordered far in advance of the anticipated need, but I’m also seeing companies partnering and pooling their orders to get more favorable positions in delivery times. Overall, I expect to see some ‘spot’ improvements in certain categories, while others are still going to continue experiencing long lead times well into 2024.

Ryan Baumann, Kohler: Meeting the demands of our data center clients is of the utmost importance. Kohler has not only made long-term capital and human resource investments towards maintaining a superior level of customer care, but has also developed an extensive SIOP methodology to ensure that all requirements of data center customers are met and projects are centered around key deliverables that guide all production activities.

Simultaneously, our team collaborates with procurement teams at some of the world’s leading engineering companies, utilizes the latest scheduling software, parts planning, and VMI (vendor managed inventory or stocking programs) programs are deployed to ensure that data center programs are delivered on time. The aim, ultimately, is to ensure that all requirements of data center customers are met, without fail, no matter the size of the project.

Don MacNeil, EdgeConneX: Supply chain issues have certainly improved in 2023. Specifically, the supply chain has returned to a higher degree of predictability, but still has a way to go towards getting back to pre-covid intervals.

Data center providers and infrastructure vendors are better aligned on timelines so that expectations can properly be established on delivery dates. Confidence in those dates alleviates the biggest challenge for providers regarding planning and customer commitments. At the same time, some of the extended delivery dates experienced during Covid have been corrected and reduced.

Adam Compton, Schneider Electric: Supplies have improved for some products to pre-pandemic levels. Expectations for supply have also re-adjusted. The race back to improved timelines has been a boon for customers who can now either return to their preferred brands/solutions, or can play vendors off each other as to who can move quickest to get the prize.

Large system metals are still a challenge. Within our business, battery chemistries are under review because of competition for the same materials vs much larger industries. In addition, different and innovative battery chemistries can lead to better outcomes for efficiency, cost, and sustainability.

NEXT: Will AI, AR and robotics have a role in data center automation?  

Keep pace with the fact-moving world of data centers and cloud computing by following us on Twitter and Facebook, connecting with DCF on LinkedIn, and signing up for our weekly newspaper using the form below:

About the Author

Rich Miller

I write about the places where the Internet lives, telling the story of data centers and the people who build them. I founded Data Center Knowledge, the data center industry's leading news site. Now I'm exploring the future of cloud computing at Data Center Frontier.

Sponsored Recommendations

Tackling Utility Project Challenges with Fiberglass Conduit Elbows

Explore how fiberglass conduit elbows tackle utility project challenges like high costs, complex installations, and cable damage. Discover the benefits of durable, cost-efficient...

How Deep Does Electrical Conduit Need to Be Buried?

In industrial and commercial settings conduit burial depth can impact system performance, maintenance requirements, and overall project costs.

Understanding Fiberglass Conduit: A Comprehensive Guide

RTRC (Reinforced Thermosetting Resin Conduit) is an electrical conduit material commonly used by industrial engineers and contractors.

NECA Manual of Labor Rates Chart

See how Champion Fiberglass compares to PVC, GRC and PVC-coated steel in installation.

Cadence Design Systems
Source: Cadence Design Systems

Implementing AI Safely and Sustainably in Data Centers

Mark Fenton, Product Engineering Director at Cadence Design Systems, explains why tools like digital twins will be essential for data centers to meet AI goals sustainably.

White Papers

Dcf Opus Wp Cover 2022 04 25 10 14 50 300x235

Hybrid and Multi-Cloud IT Executive Buyer’s Guide

April 27, 2022
Opus:Interactive outlines best practices and provides checklists for assessing your hybrid and multi-cloud needs.